Cooler than normal temperatures combined with
above normal rain and snow is creating a
situation where significantly higher than normal
Kootenai River flows are more likely in the
coming weeks.
The U.S. Army Corps of Engineers has created
water storage space for greater than normal
inflows by drafting the Koocanusa Reservoir down
to 2,354 feet in elevation, approximately 100
feet below capacity, on the reservoir side of
Libby Dam, Libby, Mont. The Corps is targeting a
reservoir elevation of 2,348-2,351 feet by the
end of April. The reservoir will continue to be
drafted at a rate of roughly one foot per day
until the start of reservoir refill, projected
for the first or second week of May.
Current high-elevation snowpack is 128 percent
of normal and lower-elevation snowpack is 153
percent in the Kootenai River basin. The
National Oceanic and Atmospheric Administration
forecast is for cooler than normal temperatures
through June with continued higher than normal
precipitation through May.
Generally upper river runoff is regulated by
Libby Dam, while lower river runoff is mostly
unregulated since it flows into the Kootenai
River below the dam. The Corps’ flood risk
management operation is to retain as much
Kootenai River flow as possible behind Libby Dam
while the downstream unregulated tributaries,
which are forecasted to flood, pass as much of
their spring snowmelt and rain flows as
possible. It is likely that Kootenai River flows
may be at or above flood stage from unregulated
tributary flows alone.
“Forecasts suggest we could see significant
rapid rises in reservoir elevation, up to eight
feet per day, by mid-May through mid-July,” said
Joel Fenolio, Upper Columbia Senior Water
Manager for the Army Corps of Engineers. “The
Kootenai River may be at or near flood stage for
a period of time starting mid-May. Downstream
tributaries to the Kootenai which are not
controlled by Libby Dam, such as the Yaak, Moyie
and Fisher Rivers, are expected to be at or
above flood stage as well.”
Residents and businesses in the river basin
should be prepared for potentially swift water
rises in a relatively short period of time once
snowpack begins to melt.
The Corps is regulating Libby Dam for flood risk
management, closely monitoring weather
conditions, snowpack readings and inflows to
mitigate flood risk downstream.
Public information meetings for Libby Dam
operations are scheduled for:
• May 9 at the Kootenai River Inn, Bonners Ferry, Idaho, at 7
p.m.
• May 12 at Libby City Hall, Libby, Mont., at 7 p.m.
|